Building consent: when you need one and when you don't
The question "do I need a consent?" has two honest answers: "probably not for small jobs" and "check anyway". Plenty of everyday work, from replacing a window like for like to laying ceiling insulation, does not need a building consent. But not needing one is different from not having to follow any rules, and in Auckland there is often a second consent, under the Resource Management Act, that catches people out.
This article explains how the system is laid out so you can ask better questions of the council, a designer or a builder.
Three separate questions
Most confusion comes from mixing up three different approvals:
- Building consent, under the Building Act, which is about whether the work will meet the Building Code.
- Resource consent, under the Auckland Unitary Plan, which is about land-use rules such as boundaries, site coverage, overlays and earthworks.
- Licensing, which determines who may carry out particular work, regardless of consent.
A project can need any combination. A deck can need no building consent and still need a resource consent. A small structure can be exempt from both but still have to comply with the Building Code.
Schedule 1: the exemption list
Schedule 1 of the Building Act 2004 lists building work that does not require a building consent. Auckland Council's consent exemptions page also points to a separate route: if work does need consent but is minor or low risk, the council can consider granting an exemption. It offers a way to place a record of work you believe is exempt on your property file, and lists a granny flat exemption that applies if certain conditions are met.
Because the details of each Schedule 1 item (sizes, heights, distances, materials) are specific, it is worth reading the current MBIE guidance for your job rather than relying on general rules. The council itself recommends getting advice from a building professional before deciding that work is exempt, and notes that you can still apply for a building consent even if the work is exempt.
Examples from Auckland Council's guidance
Two common jobs show how the layers work.
Decks. The council's guide to building a deck says a deck up to 1.5 m high does not need a building consent, though it may still need a resource consent depending on the Unitary Plan. A deck more than 1 m high must have a handrail. Whatever the height, the work must comply with the Building Code, and foundations close to public drains must not damage them. The council has an online tool for checking, which does not apply to decks above the ground floor or on a steep, sloping section.
Retaining walls. Its retaining wall guide points out that you may need a resource consent if there are significant earthworks, because earthworks can cause land instability and damage your property and your neighbours'. On a slope, that deserves real attention.
Insulation. According to the building.govt.nz guidance on insulating existing homes, no building consent is needed for ceiling or floor insulation, but external wall insulation needs building consent, or written confirmation from the council's building inspector that it is not required.
DIY and owner-builders
If you are doing the work yourself, the council's page on building work you can do yourself sets out the main rules:
- If a project does not need a building consent, you as the owner are still responsible for making sure it complies with the Building Code.
- If a resource consent is required, it must be in place before building work starts.
- Some work must be done by a professional even when no consent is needed.
- Owner-builders may carry out certain restricted building work on their own home if they live in it or will live in it, do the work themselves or with unpaid help, and have an interest in the land or building.
- The exemption is for genuine owner-occupiers and cannot be used for homes built or renovated mainly for sale or rent. You may only use it on a different property once three years have passed since completing restricted building work on the previous one.
- Electrical work, gasfitting, plumbing and drainlaying are not covered by the owner-builder exemption unless you hold the right licence. Licensed professionals must carry out and certify those.
What if the work is already done without consent?
Auckland Council's page on a Certificate of Acceptance describes the retrospective route. A certificate is proof that unconsented work meets the Building Code, but it does not have the same value as an approved building consent. You can apply only for work built without consent from 1 July 1992 onwards, and the council suggests a pre-application meeting first to find out whether building or resource consent is needed. The application may need a building report from a chartered professional engineer, registered architect or a registered or accredited building surveyor, together with owner statements, invoices, photographs and similar evidence.
This is why it pays to be careful before starting. Fixing unconsented work after the fact usually means more investigation and more cost than checking first.
A simple way to decide
Before you start any project, work through these steps:
- Describe the work in specific terms: size, height, location, materials.
- Check the Schedule 1 guidance and the council's online tools.
- Check the Unitary Plan rules for your zone and any overlays, such as special character or heritage areas.
- Ask whether any part of the job needs a licensed tradesperson.
- If the answer is still unclear, ask the council in writing and keep the reply.